Construction Update – Feb 3, 2022

Boiler Project

Boilers are assembled and in place. Final gas piping is being completed. Once the gas lines are complete inside the building by the SCA, ConEdison will come out to hook up to the external pipes.  This project is expected to be complete in the next 6 weeks give or take. The temporary boiler will be removed once complete, hopefully by late spring. 


Roof and External Brickwork

We are still awaiting the insulation for the roof. In the meantime some brick raking and mortar replacement is being worked on. 

Window Project

The SCA is continuing to work on building the widow specifications. The team is hopeful they can finalize a window design before the end of the school year. Lead time on manufacturing will depend on the design and material availability. Window replacement will not begin until all windows have been manufactured and delivered.